Wednesday, July 26, 2017


  


Scope of Work
Cianbro is the Construction Manager for renovations to the Cumberland County Civic Center. The renovations/additions will increase the building by approximately 20,000 sf.

Project Details
  • Constructing a new truck entrance and loading dock area
  • Enclosing the open building corners allowing entries at the sidewalk levels
  • Constructing new lobbies including stairs, elevators, and escalators
  • Expanding the concourses to include additional restrooms and concession and merchandise areas
  • Constructing private suites and club team offices, administrative offices, locker rooms, and a larger ticket lobby
  • Replacing the roof accessed AHU’s 
  • Demolishing and replacing all electrical and low voltage
  • Retrofitting the 7,000 arena seats
  • Enhancing the existing building facades
  • Upgrading the Free Street elevation with new pedestrian lighting and graphic panels
  • Landscaping, sidewalks and building sinage
  

Unique Challenge



The renovations will be completed in three phases. The first two phases will be completed while the facility is 100% operational. Coordination of street closures and deliveries will be essential since the building is blocked off on one side with a parking garage and the remaining three sides have streets within feet of the building..

Project Information

Owner:
Cumberland County

Type of Project:
Commercial & Institutional

Construction Schedule:
Start: August 2012
Complete: October 2013

Location:
Portland, ME