Scope of Work
Cianbro managed the construction of the state-of-the-art, 510,000 sf Poland Spring Water Bottling Plant.
Project Details
Managed the construction in two phases
Phase I—270,000 sf of bottling and warehouse space and 12,500 sf of office space
Phase II—240,000 sf of warehouse space
Performed constructability reviews
Supplied over 2,500 tons of structural steel
Erected 1,285 tons of structural steel
Placed 510,000 sf of flat slab concrete
Coordinated construction around the installation of process equipment
Installed a wet well for PH neutralization system which included cofferdams
Self-performed all source water piping including 12,000 ft of 8-inch TIG welded stainless steel pipe and 16,000 ft of 4-inch computerized orbital welded stainless steel pipe
Unique Challenge
Cianbro successfully met logistical challenges of this fast-track project by beginning construction during the winter months while design was ongoing and coordinating construction around the installation of process equipment.
Project Information
Owner:
Perrier Group Of America
Type of Project:
Industrial
Construction Schedule:
Phase I Completed June 2000
Phase II Completed November 2000
Location:
Hollis, ME
Related Links
Warehouse & Distribution
Fabrication & Coating
Pipe Fabrication & Coating
Equipment Fleet
Copyright 2011 by The Cianbro Companies
Contact Us
|
Plan Room
Vendors & Suppliers
|
Privacy Statement
|
Terms Of Use
2012 by Cianbro Corporation
Terms Of Use
Privacy Statement
Login