Solutia Incorporated Plant Expansion
Scope of Work
Cianbro fabricated and erected two structural steel buildings to expand Solutia’s manufacturing plant in Springfield, Massachusetts.
Project Details
Fabricated and erected 165 tons of structural steel
Erected two steel buildings (# 99 and # 136)—totaling 12,000 sf
Installed roof joists and purlins
Installed “Q” decking on the second and third levels of building # 99
Placed 156 cy of concrete floors
Installed “Q” decking on the mezzanine level of building # 136
Installed utility penetrations in the decking
Installed four air-handling units
Coordinated daily work activities with the subcontractors
Unique Challenge
The Cianbro team safely managed rigging challenges that included erecting 60-ft beams within an extremely limited work area.
Project Information
Owner:
Solutia Incorporated
Type of Project:
Industrial
Construction Schedule:
Completed April 2001
Location:
Springfield, MA
Related Links
Fabrication & Coating
Pipe Fabrication & Coating
Equipment Fleet