Scope of Work
Cianbro reconstructed Berths 5 & 6 at Dundalk Marine Terminal.
Project Details
Demolished and removed 1,313 lf of pile-supported wharf including pavement, railroad tracks, crane rails, wharf appurtenances, timber and concrete relieving platforms, wood sheet piles, and 3,600 timber, concrete, and steel shell pipes
Excavated and stockpiled 5,500 cy of ballast fill
Removed existing utilities and provided temporary drainage and water
Removed and disposed of one container crane at nearby Seagirt Marine Terminal
Constructed 1,327 lf of new wharf including 503 lf of steel master pile bulkhead retained by 106 grouted soil anchors and 761 lf of steel sheetpile bulkhead
Dredged 38,000 cy of bottom material in the berthing area
Drive 832, 24-inch and 295, 20-inch prestressed concrete piles
Placed 65,000 sf of precast concrete deck slabs
Placed 8,500 cy of ballast fill
Installed 2,200 lf of crane rail and 1,375 lf of track rod
Performed associated utility and electrical work
Installed fender system and pavement
Unique Challenge
Using it’s extensive experience in marine construction, the Cianbro team performed this project at an operating, high-traffic, marine terminal while maintaining and protecting traffic at all times.
Project Information
Owner:
Maryland Port Administration
Type of Project:
Marine
Construction Schedule:
Completed July 2005
Location:
Baltimore, MD
Related Links
High Definition Surveying
Equipment Fleet
Shipbuilding & Offshore
Fabrication & Coating
....
Copyright 2011 by The Cianbro Companies
Contact Us
|
Plan Room
Vendors & Suppliers
|
Privacy Statement
|
Terms Of Use
2012 by Cianbro Corporation
Terms Of Use
Privacy Statement
Login