Tuesday, November 21, 2017


  


Scope of Work
Cianbro installed foundations and erected two, 1.68 MW GE wind turbines near the PAVE (Precision Avionics Vectoring Equipment) PAWS (Phased Array Warning System), at a Massachusetts Military Reservation. 

Project Details
  •  Installed two, 56 ft octagonal concrete gravity foundations which included placing a concrete mud slab, along with installing 80 tons of reinforcing steel with two anchor bolt rings, as well as placing 850 cy of total concrete
  • Off-loaded two, 1.68 MW GE wind turbines that each  included 80 meter towers, a hub, blades, and a nacelle
  • Erected three tower sections
  • Assembled the hub and blades on the ground then erected the hub/rotor assembly as one lift to the already erected nacelle
  

Unique Challenge



The project site is located within an active military base, and was constructed during peak tourist season on Cape Cod. To minimize the project’s footprint, each site had minimal space for laydown and installation activities, requiring precise coordination with transportation for all major components.

Project Information

Owner:
United StatesAir Force 

Type of Project:
Onshore

Construction Schedule:
Completed September 2013

Location:
Bourne, MA