Thursday, May 17, 2012


Scope of Work
Cianbro constructed the 115/34.5 kV substation and control house.

Project Details
  • Erected all structural steel
  • Installed 2 dead-end structures
  • Installed 7 bus supports
  • Installed 5 switches, 1 circuit switcher, and 2 breakers
  • Installed 2 station service supports and all associated equipment
  • Pulled and terminated 25,000 feet of cable
  • Installed 1,000 feet of bus and all associated support and equipment
  

Unique Challenge



Cianbro constructed the substation during the harsh winter months. In addition the inclement and unpredictable New England weather challenged the schedule-driven project.

Project Information

Owner:
Public Service of New Hampshire

Type of Project:
Electrical Transmission & Distribution

Construction Schedule:
Completed April 2006

Location:
Ashland, NH