Thursday, May 17, 2012
About Us
Projects & Markets
News & Media
Careers
Contact Us
Projects & Markets
Transmission, Substation & Distribution
115 kV Gas-Insulated Fore River Substation
Scope of Work
Cianbro constructed the new Gas-Insulated Substation for Central Maine Power Company on the Portland Waterfront, the first of its kind for the State of Maine.
Project Details
Installed conduit on Commercial Street, Veteran’s Intersection and St. John Street
Installed 9,600 lf of concrete duct bank comprised of over 70,000 lf of six-inch conduit and 2,000 cy of concrete
Completed all civil construction
Constructed transformer and GIS foundations
Built splice manholes over 115 kV Pipe Cable
Installed conduit and ground grid
Set substation transformers
Set Control house/Switchgear Building
Installed Oil Pump Plant for 115 kV cable (Sewall Street Substation)
Installed GIS Equipment
Installed and Spliced 115 kV Pipe Type Cable
Unique Challenge
The substation project had many unique challenges due to its unique positioning on the Portland Waterfront and tight site constraints. Cianbro worked with the Louis Berger Group to engineer a path to install the new duct bank in-order to avoid conflict with other utilities, coordinated work activities to accommodate the 30,000 vehicles per day that pass throughout the area, weaved through old cobblestone roads and turn-of-the-century utilities, remained sensitive to the communities’ needs; and interacted with over four dozen businesses around the substation site.
Project Information
Owner:
Central Maine Power Company
Type of Project:
Electrical Transmission & Distribution
Construction Schedule:
Completed July 2005
Location:
Portland, ME
Related Links
Fabrication & Coating
Wind Energy Services
Power Generation & Energy
Equipment Fleet
Copyright 2011 by The Cianbro Companies
Contact Us
|
Plan Room
Vendors & Suppliers
|
Privacy Statement
|
Terms Of Use
2012 by Cianbro Corporation
Terms Of Use
Privacy Statement
Login