345/115 kV Scobie Pond Substation
Scope of Work
Cianbro replaced the 115 kV substation with a new breaker and a half substation.
Project Details
Constructed all electrical power and controls for the new control house
Erected yard structural steel including four dead end structures, 22 switch stands, 32 bus support stands, and 12 miscellaneous stands
Installed yard equipment including 11 breakers, 30 CCVTs, 22 manual switches, six motor operated switches, 141 station post insulators, and 24 lightning arresters
Pulled and terminated 80,000 lf of cable
Installed 5,500 lf of aluminum bus and supports
Performed electrical power and control modifications and additions to the existing 345 kV control house
Unique Challenge
Cianbro performed all work in an existing energized 115/345 kV substations.
Project Information
Owner:
Public Service of New Hampshire
Type of Project:
Electrical Transmission & Distribution
Construction Schedule:
Completed August 2006
Location:
Londonderry & Derry, NH
Related Links
Fabrication & Coating
Wind Energy Services
Power Generation & Energy
Equipment Fleet