Kibby Wind Power Project – Substation
Scope of Work
Cianbro provided EPC services for the construction of a 34.5 kV – 115 kV substation that concentrates and upgrades the power from the wind towers to Central Maine Power Company’s Bigelow substation through a newly constructed transmission line.
Project Details
Provided engineering services in accordance with the Owner’s specifications
Procured all electrical and mechanical components with the exception of the Owner supplied high voltage transformer and DVAR’s
Installed all civil and structural components
Installed all electrical components
Installed all power and controls
Provided engineering specifications and guidance throughout the commissioning of the project
Cianbro constructed the Kibby Substation in conjunction with the 27.6 mile 115 kV Transmission Line
Unique Challenge
The Kibby Substation project provided unique challenges including environmental sensitivity, mountainous terrain, power quality issues, and an extremely aggressive schedule working in remote areas.
Project Information
Owner:
TransCanada
Type of Project:
Electrical Transmission & Distribution
Construction Schedule:
Completed September 2009
Location:
Kibby Township, ME
Related Links
Fabrication & Coating
Wind Energy Services
Power Generation & Energy
Equipment Fleet