Scope of Work
Cianbro provided a complete electrical upgrade for the pumping station including unit substations, motor control centers, a programmable logic controller, variable frequency drives, transformers, disconnects, and manual motor starters.

Project Details
  • Installed 600 amp motor control center
  • Installed 30 KVA transformer, a 3 KVA transformer and two 60 amp disconnects
  • Installed 10 manual motor starters and 2 variable frequency drives
  • Furnished and installed 14,000 LF of conduit, 62,224 LF of wire and 6,240 terminations.
  

Unique Challenge



Cianbro installed a duct bank containing 24 – 4 inch conduits that branched off into two separate duct banks each containing 12 – 4 inch conduits, which ran to the underside of the switchgear. The site was below ground level and filled with water causing saturated, muddy working conditions.

Project Information

Owner:
Baltimore County Department of Public Works

Type of Project:
Water / Waste Water

Construction Schedule:                             
Completed September 2007 

Location:
White Marsh, MD