Project Detail
X
GO

Distribution Line Rebuilds

Location:
Withheld Upon Owner Request
Completed:
2017

Scope of Work

Cianbro performed inspection driven rebuilds on 12.47/7.2 kV distribution lines in various locations. The rebuild work included pole and anchor setting, framing, transfers, installation of animal guards, installation of down grounds, and pole removals. The pole removals were limited to the portion of the pole above the communications space or those that required removal of the entire pole.

Project Details

  • Location #1:
    • 1 - 35 feet class 5 wood pole
    • 190 animal guards
    • 13 anchors
  • Location #2:
    • 1 - 45 feet class 3 wood pole
    • 4 - 40 feet class 4 wood poles
    • 2 - 35 feet class 5 wood poles
    • 5 anchors
    • 312 animal guards
  • Location #3
    • 5 - 40 feet class 4 wood poles
    • 21 - 96 inch wood arms
    • 74 cut outs
    • 345 animal guards

Lean, Innovative, and Unique Project Solutions

Cianbro performed all rebuild work on energized lines along the roadside requiring substantial traffic control and safety measures.