Return
Location:
Maine
Completed:
2018

Composite Panel Replacement

Scope of Work
Cianbro removed and replaced 800 tubes in the form of panels, performing over 1,600 composite tube welds, with 100 percent X-ray acceptance.
Project Details
  • Performed 1,600 tube welds
  • Removed and replaced the secondary and tertiary wind box
Lean, Innovative and Unique Project Solutions
Cianbro's project team staged a "fabrication shop" in the basement of the boiler with clamping sawhorses and mounted bench grinders, allowing for Lean fabrication and preparation of tube panels to be installed. Pre-made sponges and purge cups were procured to allow for a more Lean FME and documentation system during wall preparation.
No items found.

Our Offices
Corporate Headquarters
P.O. Box 1000
Pittsfield, ME 04967
207-487-3311
info@cianbro.com

Email Us

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.